Syed Rashid Ahmed ButtShaanxi Chengda Industrial Furnace Co., Ltd. completed the commissioning of electric arc furnace, the workers carefully cooperated with Chengda engineers to learn and operate the equipment, showing the deep friendship and excellent cooperation between the people of China and Pakistan. -
AboubacarAfter more than 1 month of intense production and debugging, 2 sets of heat exchange flue gas settling chamber equipment has been successfully put into operation ~ All the personnel involved in the project have worked hard! ~ -
Ji-hwan【 Warm congratulations 】 Shaanxi Chengda Industrial Furnace Manufacturing Company in South Korea, North Chungcheong County precious metal smelting furnace equipment installation and careful manufacturing and strict commissioning, looking forward to the future in more fields to achieve mutually beneficial win-win cooperation!
Ferronickel Submerged Arc Furnace Equipment for Nickel Ore Smelting Plant Projects
| Model Number | CD-NI-SAF | Rated Power | Customized |
|---|---|---|---|
| Furnace Shell Size | Customized | Melting Temperature | 1450-1550°C |
| Electrode System | Hydraulic Slipping | Cooling | Water Cooled Hood And Flue |
| Highlight | Ferronickel submerged arc furnace equipment,Submerged arc furnace for nickel ore smelting,Ferroalloy refining equipment for smelting plants |
||
Product Overview
This ferronickel submerged arc furnace is supplied as a complete smelting line for nickel ore, including charging and dust collection system, water-cooled flue, tapping system, hydraulic system, electrode holder and discharge arrangement.
Technical Parameters
| Item | Value |
|---|---|
| Smelting duty | Ferronickel |
| Annual output | 600,000 t/y class |
| Electrode system | Hydraulic slipping with holder and sleeve |
| Cooling | Water-cooled hood and flue |
Main Components
- Charging system with dust collection hood
- Water-cooled flue duct and settling chamber
- Discharge system with hydraulic gate valve
- Electrode holder system and hydraulic power unit
- Tapping and ladle transfer arrangement
Operation
Ore, reductant and flux are batched and fed through roof chutes. Arc and resistance heating reduce the charge, and ferronickel is tapped at fixed intervals. Electrode position, power input and slag condition are monitored continuously to keep the furnace on its power programme.
Scope of Delivery
Furnace proper, charging and batching system, water-cooled hood and flue, tapping system, hydraulic station, electrical control, drawings, erection supervision and commissioning.